As a successful project manager, you’re most likely a multi-tasker who is generally pretty good at juggling many balls, or tasks, at once. Before starting any project, you’d agree that you need to have a firm grasp of the task at hand, knowing what the end user needs from you.
However important that first step is, that’s only the beginning. You have to then conceptualize the steps, create a plan, foreseeing the need for a Plan B, C or D – just in case. Next you’re on to specifying a project duration, and then, upon commencing, keeping all the resources, including team members, finances, etc., moving along in a nice and tidy fashion all while maintaining an overall sense of professional decorum. No sweat, right?!
Enter project management planning and the tools and concepts that will help you be up to the challenge. Taking the right steps in the most efficient order assists your team in delivering the best possible outcome in the estimated amount of time. At the outset of the project, you must determine which tasks are stand alone and can be worked on separately, and which assignments depend on another step having already been accomplished and so forth.
You know that the individual aspects of any project are somehow interconnected. Figuring out the “how” that works best for your specific project will help you and your team start, stay and productively stop on the same page. These task relationships are called dependencies.
Project Scope Analysis
The connections between tasks and the priority of the task associations determine the project’s scope and time frame. When initially needing to conceptualize the “big picture” of what needs to be accomplished, working through the following steps will help you see that picture clearly:
solidify the project scope with the client and additionally with your team and management
- determine the best, most logical order of tasks
- evaluate the critical path (decide on a specific tool set in an effort to govern the project)
- identify what resources are available to you
- incorporate any scheduling issues into the plan
- supervise the overall plan throughout, and finally,
- search for ways to compress the schedule and save money along the way if possible.
Need more information? We have it for you. Read more about project scope or watch a tutorial about how to estimate the duration of a project, aka, a critical path.
4 Task Dependency Types
Even new project managers have likely already encountered the concept of dependencies. For instance, if you have ever wanted to enroll in a college course there may have been a prerequisite course. Meaning one class needs to be completed before taking another for which it is a prerequisite. To be clear, a prerequisite refers to something that must happen before something else can occur; hence, in this scenario, creating a dependent relationship from one class to the prior class.
Back to project management, mapping out all of the assignments, seeing how tasks start/stop/overlap and understanding dependencies is crucial to staying within your project’s parameters. Let’s look at 4 types of task dependencies to consider as you conceptualize and execute any plan for a new project.
- Finish-to-Start – This approach is the one with which most people are familiar. Step 1 of the project must be totally completed before Step 2 can begin: making Step 2 dependent on the completion of Step 1. Keeping an eye on each team member’s progress in this type of dependency is critical for keeping the entire project on target.
- Start-to-Start – In this dependency, there will be a Step 1 that must already be under way, however, it does not have to be completed in order for Step 2 to begin. They may occur simultaneously, as long as Step 1 started first. A benefit of this dependency type is that work overlaps, moving the project along more quickly.
- Finish-to-Finish –You may have a situation in which one step can’t stop before another step does. While there may not be any specific time frame for the endings, with simultaneous tasks in motion, the completion of these tasks must take place at the same time.
- Start-to-Finish –This approach dictates that Step 2 can’t finish until Step 1 starts. The Start-to-Finish approach is the most complex and would be used infrequently.
Here’s a chart that will help you to visualize these dependencies.
Also, you can check out this video that walks you through and helps you understand each type of dependency on the list. The presenter uses several different scenarios as examples while showing not only how to understand each dependency, but also how to include lags that may occur along the way.
In the big picture, a lag is an interruption in the progression of a project. Smaller picture, it’s a delay in the completion of a task which affect other tasks. These disturbances can add time to either or both of the task’s start or finish date – effecting activity of either its predecessor or successor.
Task dependencies can occur both in the same project between tasks as well as between tasks from different projects. In either case, predecessor/successor dependencies are created. For example, it may be that your project is considered “Step 2”, so you’ll be waiting on the team to complete Step 1. Your dependencies may also be related to the available company resources and/or the priority your leadership places on your project.
Project Management Planning Tools
Earlier, I mentioned that there were tools that can help you plan your project. Keep in mind that there’re numerous software possibilities that may assist with project planning, however, they’re not all are created equally.
Many will provide a customizable, easy-to-use interface, timeline view, reports and social media capability with email integration, mobile connectivity and more. However, not every alternative out there includes a dependency function.
While not an exhaustive list, here are a few that allow for dependencies in addition to other organizational and time management aspects.
- 5PM (software review) has a sub-tasks component that walks you through how to set up your parent and dependent tasks. Their website states, “The Timeline visualizes the task dependencies using connecting arrows. Moving the parent tasks will move all the dependent tasks as well, so re-scheduling is a breeze.”
- Wrike (software review) has a Timeline (Gantt-Chart) feature “that lets you view your project schedule and set dependencies in real time with easy adjustments to keep your team on track.”
- LiquidPlanner (software review) has a Dependencies and Wait Time function available with its Small Team, Professional and Enterprise options. The software uses what they call, “Priority-based scheduling”, saying that it “generally eliminates the need to create dependencies between tasks that are owned by the same person. That’s because in the absence of any delays or dependencies, the earliest start date of a task you own automatically equals the earliest finish of your previous task in the priority order.
If you guessed that this means the LiquidPlanner software only allows for finish-to-start dependencies, you’d be right! If this is your preferred project management process, then the features like a dependency icon, alerts, status updates and a Wait Time function will especially help you keep your team on task for your project.
Additional Resources and Wrap-Up
As you continue learning about the types of dependencies and how they affect your project management, check out these articles that will help you to select the right management software for you! Microsoft Project Online Software Review | Top 3 Software Alternatives to Microsoft Project Online
The post Understanding Task Dependency Types in Project Management appeared first on Project-Management.com.